Subway line U6 – Construction phase U6/9 – Part 2 – Perfektastraße – Erlaaer Straße

Project Description

Project description:
Subway line U6: km 3.984 – km 5.377
Segment length: 1,393 m
Total track length: 3,388 m

Essential features:
Perfektastraße subway station with side platforms approx. 3.00 m above terrain, on embankment partly with retaining walls and partly on support structure; station building on the south end of the station, built of in-situ concrete.
Subway station Erlaaer Straße with side platforms approx. 3.00 m above terrain, on embankment and on support structure in some parts; station building on the south end of the station, built of in-situ concrete.
Tracks on embankment and terrain level
Bridge across Carlbergergasse
Wildlife crossing (bridge)

The above facilities were built during continued operation of the tram line 64 with temporary tracks in the area Perfektastraße and Erlaaer Straße.

Client: Wiener Linien GesmbH & Co KG
Contact person: OBR Dipl. Ing. Schöft, Head of Department
B67 –Bautechnische Angelegenheiten der U-Bahn (Subway Construction/Engineering)
Phone:  +43 1 7909-67000
Project: Subway line U6, building section 9 – part 2 – Perfektastraße – Erlaaer Straße
Project area: Vienna
Net costs: €4.5 mill.
Planning period:1989 to May 1995
Construction period: May 1991 to April 1995

Scope of works:

Traffic planning
Submission planning
Planning of construction phases
Planning the relocation of installations
Planning of track-side equipment
Tender planning
Detailed planning

Architectural design: architect Winkler, U-Bahn group of architects and Professor Gsteu

Category

U-bahn / Straßenbahn